Goodijk, J.D. (2019) Explaining cost overrun in infrastructure projects. Master thesis.
|
Text
Master_thesis_final_version.pdf Download (1MB) | Preview |
Abstract
Cost overrun is common among infrastructure projects, and can be a result of different causes. There is a research gap in which configuration of conditions have an effect on cost overrun in public-private partnerships (PPPs). The conditions that will be used to analyze the outcome (cost overrun) are: (1) contract type; (2) type of stakeholder management; (3) proper risk allocation; (4) project size. The research method is a qualitative comparative analysis (QCA). The results indicate that D&C contracts in combination with an improper risk allocation and a relative small project size (between €120 million and €410 million) lead to cost overrun. The results also give a solution for cost underrun, consisting of two solution terms. The DBFM contract in combination with process management and a proper risk allocation, and a DBFM contract with a proper risk allocation and a large project size lead to cost underrun.
Item Type: | Thesis (Master) |
---|---|
Degree programme: | Environmental & Infrastructure Planning |
Supervisor: | Verweij, S. and Leendertse, W.L. |
Date Deposited: | 23 Apr 2020 05:47 |
Last Modified: | 23 Apr 2020 05:47 |
URI: | https://frw.studenttheses.ub.rug.nl/id/eprint/3126 |
Actions (login required)
View Item |